Assessment Objective
Determine if:
- CP-02(02)[01] capacity planning is conducted so that the necessary capacity exists during contingency operations for information processing;
- CP-02(02)[02] capacity planning is conducted so that the necessary capacity exists during contingency operations for telecommunications;
- CP-02(02)[03] capacity planning is conducted so that the necessary capacity exists during contingency operations for environmental support.
Assessment Methods
Examine
- Contingency planning policy
- procedures addressing contingency operations for the system
- contingency plan
- capacity planning documents
- system security plan
- other relevant documents or records
Interview
- Organizational personnel with contingency planning and plan implementation responsibilities
- organizational personnel responsible for capacity planning
- organizational personnel with information security responsibilities
Linkede sager
| Linktype | Sag |
|---|---|
| blocks | CP-02(02) [H] Capacity Planning |