+Article 14 2

Article 14 2

2.   Operators shall initiate the first type 2 LDAR survey of all components under their responsibility in accordance with the LDAR programme as soon as possible from 4 August 2024.

In any event, operators shall carry out the first type 2 LDAR survey by 5 August 2025 for existing sites. Without prejudice to the frequencies established in Part 1 of Annex I, type 2 LDAR surveys carried out between 3 August 2022 and 4 August 2024 may be considered by operators as the first type 2 LDAR survey.

Within 9 months from the date of start of operations of new sites, operators shall carry out the first type 2 LDAR survey of all components under their responsibility in accordance with the LDAR programme.

After carrying out the first type 2 LDAR survey, operators shall carry out type 1 and type 2 LDAR surveys with the following frequencies:

(a)

for aboveground and underground components, excluding distribution and transmission networks, in accordance with the minimum frequencies set out in Part 1, point 1, of Annex I;

(b)

for components of distribution and transmission networks, in accordance with the minimum frequencies set out in Part 1, point 2, of Annex I;

(c)

for all offshore components, in accordance with the minimum frequencies set out in Part 1, point 3, of Annex I;

(d)

for all other components, in accordance with the minimum frequencies set out in Part 1, point 4, of Annex I.

1. Oversigt

,
Titel Regulering

1.1 Referencer

1.2 Identificerede krav

1.3 Relaterede standarder

2. Identificerede krav

Krav
Kilde Krav

3. Relaterede standarder

Standarder
Kilde Krav