+Article 6a 2.
|
Article 6a 2.
The framework referred to in paragraph 1 may ensure that flexible connection agreements specify at least the following:
(a)
the maximum firm injection and withdrawal of electricity from and to the grid, as well as the additional flexible injection and withdrawal capacity that can be connected and differentiated by time blocks throughout the year;
(b)
the network charges applicable to both the firm and flexible injection and withdrawal capacities;
(c)
the agreed duration of the flexible connection agreement and the expected date for granting connection to the entire requested firm capacity.
The system user connecting through a flexible grid connection shall be required to install a power control system that is certified by an authorised certifier.
1. Übersicht
| Bezeichnung |
Regulierung |
,
1.1 Referenzen
1.2 Identifizierte Anforderungen
1.3 Zugehörige Standards
2. Identifizierte Anforderungen
Anforderungen
| Quelle |
Anforderung |
3. Zugehörige Standards
Standards
| Quelle |
Anforderung |
- Builddate: 12.10.2025 00:00:00 -Doknr: CELEX:32019L0944
- EULAW -
EN: Legal acts of the European Union from EUR-Lex, https://eur-lex.europa.eu/. © European Union. Re-use is authorised by Decision 2011/833/EU, provided the source is acknowledged; the consolidated texts are licensed under CC BY 4.0 (EUR-Lex legal notice). Divided into sections and converted into the GRCA format, the wording unchanged. Only the legislation published in the Official Journal of the European Union is deemed authentic.
DE: Rechtsakte der Europäischen Union aus EUR-Lex, https://eur-lex.europa.eu/. © Europäische Union. Weiterverwendung nach Beschluss 2011/833/EU mit Quellenangabe gestattet; die konsolidierten Fassungen stehen unter CC BY 4.0 (Rechtlicher Hinweis von EUR-Lex). In Abschnitte aufgeteilt und in das GRCA-Format umgewandelt, der Wortlaut unverändert. Verbindlich sind allein die im Amtsblatt der Europäischen Union veröffentlichten Rechtsakte.
|