+Article 17 4.

Article 17 4.

The schemes for independent verification shall be established:

(a) 

in respect of installations, to give independent assurance that the safety and environmental critical elements identified in the risk assessment for the installation, as described in the report on major hazards, are suitable and that the schedule of examination and testing of the safety and environmental critical elements is suitable, up-to-date and operating as intended;

(b) 

in respect of notifications of well operations, to give independent assurance that the well design and well control measures are suitable for the anticipated well conditions at all times.

1. Übersicht

,
Bezeichnung Regulierung

1.1 Referenzen

1.2 Identifizierte Anforderungen

1.3 Zugehörige Standards

2. Identifizierte Anforderungen

Anforderungen
Quelle Anforderung

3. Zugehörige Standards

Standards
Quelle Anforderung