+Article 16 8. |
Article 16 8.Except when it coincides with other administrative stages of the permit-granting procedure, the duration of the permit-granting procedure shall not include:
(a)
the time during which the renewable energy plants, their grid connections and, with a view to ensuring grid stability, grid reliability and grid safety, the related necessary grid infrastructure, are being built or repowered;
(b)
the time for the administrative stages necessary for significant upgrades of the grid required to ensuring grid stability, grid reliability and grid safety;
(c)
the time for any judicial appeals and remedies, other proceedings before a court or tribunal, and alternative dispute resolution mechanisms, including complaint procedures and non-judicial appeals and remedies. 1. Übersicht