+Article 16 8.
|
Article 16 8.
Except when it coincides with other administrative stages of the permit-granting procedure, the duration of the permit-granting procedure shall not include:
(a)
the time during which the renewable energy plants, their grid connections and, with a view to ensuring grid stability, grid reliability and grid safety, the related necessary grid infrastructure, are being built or repowered;
(b)
the time for the administrative stages necessary for significant upgrades of the grid required to ensuring grid stability, grid reliability and grid safety;
(c)
the time for any judicial appeals and remedies, other proceedings before a court or tribunal, and alternative dispute resolution mechanisms, including complaint procedures and non-judicial appeals and remedies.
1. Overview
1.1 References
1.2 Identified Requirements
1.3 Related Standards
2. Identified Requirements
Requirements
| Source |
Requirement |
3. Related Standards
Standards
| Source |
Requirement |
- Builddate: 16.07.2024 00:00:00 -Doknr: CELEX:32018L2001
- EULAW -
EN: Legal acts of the European Union from EUR-Lex, https://eur-lex.europa.eu/. © European Union. Re-use is authorised by Decision 2011/833/EU, provided the source is acknowledged; the consolidated texts are licensed under CC BY 4.0 (EUR-Lex legal notice). Divided into sections and converted into the GRCA format, the wording unchanged. Only the legislation published in the Official Journal of the European Union is deemed authentic.
DE: Rechtsakte der Europäischen Union aus EUR-Lex, https://eur-lex.europa.eu/. © Europäische Union. Weiterverwendung nach Beschluss 2011/833/EU mit Quellenangabe gestattet; die konsolidierten Fassungen stehen unter CC BY 4.0 (Rechtlicher Hinweis von EUR-Lex). In Abschnitte aufgeteilt und in das GRCA-Format umgewandelt, der Wortlaut unverändert. Verbindlich sind allein die im Amtsblatt der Europäischen Union veröffentlichten Rechtsakte.
|