+DORA Ch. II Sec. II Art. 12 6.
|
DORA Ch. II Sec. II Art. 12 6.
6. In determining the recovery time and recovery point objectives for each function, financial entities shall take into account whether it is a critical or important function and the potential overall impact on market efficiency. Such time objectives shall ensure that, in extreme scenarios, the agreed service levels are met.
1. Overview
1.1 References
1.2 Identified Requirements
1.3 Related Standards
2. Identified Requirements
Requirements
| Source |
Requirement |
3. Related Standards
Standards
| Source |
Requirement |
|
NOREA
|
Backup Policy
Define backup policies aimed at ensuring minimum downtime, limited disruption, and loss, and put in place restoration and recovery procedures. Specify the scope of the data subject to backups and the minimum frequency of backups, based on the criticality or confidentiality of data. Determine a Recovery Time Objective (RTO) and a Recovery Point Objective (RPO) based on data criticality and overall impact on market efficiency to ensure that service levels are met in extreme scenarios.
|
|
NOREA
|
Restore Procedures
Ensure that the activation of backup systems will not jeopardize the security of ICT systems or the availability, authenticity, integrity or confidentiality of data. For example through the execution of periodic restore tests based on the backup, restoration, and recovery procedures.
Ensure that when restoring backup data using self-managed systems, that systems are used that are both physically and logically segregated from the source system to ensure protection. Furthermore, the backup systems shall be securely protected from any unauthorized access or IT corruption and allow for timely restoration. Institutions must validate that the highest level of data integrity is maintained when restoring backups.
Additionally for central counterparties: the recovery plans shall enable the recovery of all transactions at the time of disruption to allow the central counterparty to continue to operate with certainty and to complete settlement on the scheduled date.
Additionally for data reporting service providers*: the providers shall additionally maintain adequate resources and have back-up and restoration facilities in place in order to offer and maintain their services at all times.
*For definition of DRSP see: https://www.esma.europa.eu/esmas-activities/markets-and-infrastructure/data-reporting-services-providers
|
|
SCF
|
Recovery Time / Point Objectives (RTO / RPO)
Description
Mechanisms exist to facilitate recovery operations in accordance with Recovery Time Objectives (RTOs) and Recovery Point Objectives (RPOs).
Possible Solutions & Considerations
Micro-Small Business (<10 staff) / BLS Firm Size Classes 1-2
∙ Continuity of Operations Plan (COOP)
∙ Business Continuity Plan (BCP)
∙ Disaster Recovery Plan (DRP)
∙ Recovery Time Objectives (RTOs)
∙ Recovery Point Objectives (RPOs)
Small Business (10-49 staff) / BLS Firm Size Classes 3-4
∙ Continuity of Operations Plan (COOP)
∙ Business Continuity Plan (BCP)
∙ Disaster Recovery Plan (DRP)
∙ Recovery Time Objectives (RTOs)
∙ Recovery Point Objectives (RPOs)
Medium Business (50-249 staff) / BLS Firm Size Classes 5-6
∙ Continuity of Operations Plan (COOP)
∙ Business Continuity Plan (BCP)
∙ Disaster Recovery Plan (DRP)
∙ Recovery Time Objectives (RTOs)
∙ Recovery Point Objectives (RPOs)
Large Business (250-999 staff) / BLS Firm Size Classes 7-8
∙ Continuity of Operations Plan (COOP)
∙ Business Continuity Plan (BCP)
∙ Disaster Recovery Plan (DRP)
∙ Recovery Time Objectives (RTOs)
∙ Recovery Point Objectives (RPOs)
Enterprise (> 1,000 staff) / BLS Firm Size Class 9
∙ Continuity of Operations Plan (COOP)
∙ Business Continuity Plan (BCP)
∙ Disaster Recovery Plan (DRP)
∙ Recovery Time Objectives (RTOs)
∙ Recovery Point Objectives (RPOs)
SCR-CMM
Level 0 Not Performed
Practices are non-existent, based on the inability to demonstrate an implemented and operational capability. A reasonable person would conclude the control is not being performed.
Level 1 Performed Informally
SCR-CMM Level 1 criteria definitions are not available for this control:
▪ A reasonable person would conclude this control requires a structured process.
▪ At this level of maturity, the "ad hoc" nature of performing a capability informally would indicate the intent of the control is not met due to a lack of consistency and formality.
Level 2 Planned Tracked
SCR-CMM Level 2 criteria definitions are not available for this control:
▪ A reasonable person would conclude a well-defined and standardized process is required.
▪ At this level of maturity, the “requirements-driven” nature of performing the control is focused on a localized and/or regionalized implementation, not uniform and consistent across the organization.
▪ Requirements are narrowly scoped for applicability and are primarily derived from compliance obligations (e.g., laws, regulations and contracts).
Level 3 Well Defined
Business Continuity & Disaster Recovery (BCD) capabilities are standardized across the entity for applicability to People, Processes, Technologies, Data and/or Facilities (PPTDF) to ensure consistency for Technology Assets, Applications, Services and/or Data (TAASD). Capability criteria associated with this control reasonably expect the following criteria to exist:
▪ Policies and standards associated with BCD domain capabilities are formally documented and centrally-managed by the entity's Governance, Risk & Compliance (GRC) team, or similar function.
▪ Standardized Operating Procedures (SOP) associated with BCD domain capabilities are well-documented and kept current by process owners.
▪ A Business Continuity & Disaster Recovery (BC/DR) team, or similar function, is appropriately staffed and supported to implement and maintain BCD domain capabilities.
▪ Technology is leveraged to enhance the efficiency and accuracy of BC/DR operations (e.g., BC/DR planning software, Disaster Recovery as a Service (DRaaS), Orchestration and Automation Tools, etc.).
▪ The entity's Governance, Risk & Compliance (GRC) team, or similar function, works with business stakeholders and process owners to appropriately scope and reasonably implement cybersecurity and data protection controls associated with BCD domain capabilities to address Minimum Compliance Requirements (MCR) (e.g., applicable statutory, regulatory and/or contractual requirements) and Discretionary Security Requirements (DSR) (e.g., entity-required controls).
▪ An implemented and operational capability exists to facilitate recovery operations in accordance with Recovery Time Objectives (RTOs) and Recovery Point Objectives (RPOs).
Level 4 Quantitatively Controlled
Business Continuity & Disaster Recovery (BCD) capabilities, in addition to being standardized across the entity and centrally managed to ensure consistency across Technology Assets, Applications, Services and/or Data (TAASD), efforts are metrics driven to provide sufficient insight for decision makers to predict optimal performance, ensure continued operations and/or identify areas for improvement. Capability criteria associated with this control reasonably expect the following criteria to exist:
▪ Applicable SCR-CMM Level 3 (Well Defined) capabilities are implemented and operational.
▪ Metrics reporting includes quantitative analysis of Key Performance Indicators (KPIs).
▪ Metrics reporting includes quantitative analysis of Key Risk Indicators (KRIs).
▪ Scope of metrics, KPIs and KRIs covers organization-wide cybersecurity and data protection controls, including functions performed by third-parties.
▪ Organizational leadership maintains a formal process to objectively review and respond to metrics, KPIs and KRIs (e.g., monthly or quarterly review).
▪ Based on metrics analysis, process improvement recommendations are submitted for review and are handled in accordance with change control processes.
▪ Business and technical stakeholders are involved in reviewing and approving proposed changes to evolve capabilities.
Level 5 Continuously Improving
Utilize SCR-CMM Level 3 or Level 4 (if available) criteria definitions:
▪ There are no defined Level 5 criteria, since it is reasonable to assume a continuously-improving process is not necessary to operationalize this control.
▪ Level 5 capabilities should be considered “world-class” where the control builds on Level 4 capabilities, but are continuously improving through Artificial Intelligence (AI) and/or Machine Learning (ML) technologies.
▪ While it may be possible to develop responsive capabilities for this control through the use of AI and/or ML technologies, the criteria would be organization-specific to define.
|
|