+Article 59 4.

Article 59 4.

The regulatory authority located in the Member State in which the single allocation platform, the ENTSO for Electricity or the EU DSO entity has its seat shall have the power to impose effective, proportionate and dissuasive penalties on those entities where they do not comply with their obligations under this Directive, Regulation (EU) 2019/943 or any relevant legally binding decisions of the regulatory authority or of ACER, or to propose that a competent court impose such penalties.

1. Resumen

,
Título Regulación

1.1 Referencias

1.2 Requisitos identificados

1.3 Estándares relacionados

2. Requisitos identificados

Requisitos
Fuente Requisito

3. Estándares relacionados

Estándares