Activity
|
Capacity Threshold
|
|
1
|
Activities listed in Annex I to Directive 2010/75/EU
|
Above the applicable capacity thresholds set out in Directive 2010/75/EU
|
|
2
|
Activities listed in Annex Ia to Directive 2010/75/EU
|
Above the applicable capacity thresholds set out in Directive 2010/75/EU
|
|
3
|
Activities referred to in Article 2 of Directive (EU) 2015/2193 (where not covered by Annex I to Directive 2010/75/EU)
|
Combustion plants with a rated thermal input of at least 20 MW and below 50 MW
|
|
4
|
Underground mining and related operations, including the extraction of crude oil or gas either onshore or offshore (where not covered by Annex I to Directive 2010/75/EU)
|
No capacity threshold (all installations are subject to reporting)
|
|
5
|
Opencast mining and quarrying (where not covered by Annex I to Directive 2010/75/EU)
|
Where the surface of the area effectively under extractive operation equals 25 hectares
|
|
6
|
Urban waste water treatment plants
|
With a capacity of 100 000 population equivalents or more
|
|
7
|
Feed-based aquaculture
|
Exceeding an annual production capacity of 500 tonnes
|
|
8
|
Installations for the building and/or dismantling of ships, and for the painting or removal of paint from ships
|
With a capacity for ships 100 m long
|
|
9
|
Electrolysis of water for production of hydrogen
|
Industrial scale production
|