+Article 2 (2)

Article 2 (2)

‘decommissioning plan’ means a document that contains detailed information on the proposed decommissioning and covers the following: the selected decommissioning strategy; the schedule, type and sequence of decommissioning activities; the waste management strategy applied, including clearance; the proposed end state; the storage and disposal of the waste from decommissioning; the timeframe for decommissioning; the cost estimates for the completion of decommissioning; and the objectives, expected results, milestones, target dates, as well as the corresponding key performance indicators, including, where appropriate, earned-value-based indicators. The decommissioning plan is prepared by the nuclear facility licence holder and is reflected in the multiannual work programmes of the Programme.