+Article 14 Rapport d'évaluation
---+Article 14 1.
---+Article 14 2.
---+Article 14 3.
---+Article 14 4.

Article 14 Rapport d'évaluation

Article 14

Rapport d'évaluation

1.  Après avoir reçu une notification conforme à l'article 13, paragraphe 2, et en avoir accusé réception, l'autorité compétente examine si cette notification est conforme aux exigences de la présente directive.

2.  Dans les quatre-vingt-dix jours suivant la réception de la notification, l'autorité compétente:

— 
établit un rapport d'évaluation et le transmet au notifiant. Si le notifiant retire sa notification par la suite, ce retrait est sans préjudice de toute autre transmission de la notification à une autre autorité compétente,
— 
dans le cas prévu au paragraphe 3, point a), fait parvenir à la Commission, qui le transmet dans les trente jours qui suivent sa réception aux autorités compétentes des autres États membres, son rapport, accompagné des informations visées au paragraphe 4 et de tous les autres éléments d'information sur lesquels elle a fondé son rapport.

Dans le cas prévu au paragraphe 3, point b), au plus tôt quinze jours après l'envoi du rapport d'évaluation au notifiant et au plus tard cent cinq jours après la réception de la notification, l'autorité compétente transmet à la Commission son rapport, accompagné des informations visées au paragraphe 4 et tous les autres éléments d'information sur lesquels elle a fondé son rapport. Dans les trente jours qui suivent sa réception, la Commission transmet le rapport aux autorités compétentes des autres États membres.

3.  Le rapport d'évaluation indique:

a) 

si le ou les OGM concernés doivent être mis sur le marché et dans quelles conditions, ou

b) 

si ce ou ces OGM ne doivent pas être mis sur le marché.

Les rapports d'évaluation sont établis conformément aux orientations définies à l'annexe VI.

4.  Pour calculer le délai de quatre-vingt-dix jours visé au paragraphe 2, on ne tient pas compte des périodes durant lesquelles l'autorité compétente attend les informations complémentaires éventuellement demandées au notifiant. L'autorité compétente motive toute demande d'information complémentaire.

1. Vue d’ensemble

,
Intitulé Réglementation
Article 14 1.
On receipt and after acknowledgement of the notification in accordance with Article 13(2), the competent authority shall examine it for compliance with this Directive.
Article 14 2.

Within 90 days after receipt of the notification the competent authority shall:

— 
prepare an assessment report and send it to the notifier. A subsequent withdrawal by the notifier shall be without prejudice to any further submission of the notification to another competent authority;
— 
in the case referred to in paragraph 3(a), send its report, together with the information referred to in paragraph 4 and any other information on which it has based its report, to the Commission which shall, within 30 days of its receipt, forward it to the competent authorities of the other Member States.

In the case referred to paragraph 3(b), the competent authority shall send its report, together with the information referred to in paragraph 4 and any other information on which it has based its report, to the Commission no earlier than 15 days after sending the assessment report to the notifier and no later than 105 days after receipt of the notification. The Commission shall, within 30 days of its receipt, forward the report to the competent authorities of the other Member States.

Article 14 3.

The assessment report shall indicate whether:

(a) 

the GMO(s) in question should be placed on the market and under which conditions; or

(b) 

the GMO(s) in question should not be placed on the market.

The assessment reports shall be established in accordance with the guidelines laid down in Annex VI.

Article 14 4.
For the purpose of calculating the 90 day period referred to in paragraph 2, any periods of time during which the competent authority is awaiting further information which it may have requested from the notifier shall not be taken into account. The competent authority shall state the reasons in any request for further information.

1.1 Références

1.2 Exigences identifiées

1.3 Normes associées

2. Exigences identifiées

Exigences
Source Exigence

3. Normes associées

Normes
Source Exigence
  • Builddate: 27.03.2021 00:00:00 -Doknr: CELEX:32001L0018
  • EULAW -

    EN: Legal acts of the European Union from EUR-Lex, https://eur-lex.europa.eu/. © European Union. Re-use is authorised by Decision 2011/833/EU, provided the source is acknowledged; the consolidated texts are licensed under CC BY 4.0 (EUR-Lex legal notice). Divided into sections and converted into the GRCA format, the wording unchanged. Only the legislation published in the Official Journal of the European Union is deemed authentic.

    DE: Rechtsakte der Europäischen Union aus EUR-Lex, https://eur-lex.europa.eu/. © Europäische Union. Weiterverwendung nach Beschluss 2011/833/EU mit Quellenangabe gestattet; die konsolidierten Fassungen stehen unter CC BY 4.0 (Rechtlicher Hinweis von EUR-Lex). In Abschnitte aufgeteilt und in das GRCA-Format umgewandelt, der Wortlaut unverändert. Verbindlich sind allein die im Amtsblatt der Europäischen Union veröffentlichten Rechtsakte.