PE-09 Power Equipment and Cabling
›
Standard - PE-09(01) Redundant Cabling
+PE-09(01) Redundant Cabling
PE-09(01) Redundant Cabling
Control
Employ redundant power cabling paths that are physically separated by [Assignement: distance].
Discussion
Physically separate and redundant power cables ensure that power continues to flow in the event that one of the cables is cut or otherwise damaged.
Assessment Objective
redundant power cabling paths that are physically separated by [Assignement: distance] are employed.
Assessment Method
Examine
Physical and environmental protection policy procedures addressing power equipment/cabling protection facilities housing power equipment/cabling system security plan other relevant documents or records
Interview
Organizational personnel with the responsibility to protect power equipment/cabling organizational personnel with information security responsibilities
1. Vue d’ensemble
Intitulé
Norme
1.1 Références
1.2 Exigences identifiées
1.3 Réglementations associées
2. Exigences identifiées
Exigences
Source
Exigence
3. Réglementations associées
Réglementations
Source
Réglementation
Tickets liés
Liens
Type de lien
Ticket
is blocked by
PE-09(01) Redundant Cabling – Assessment Procedure
is blocked by
Redundant Cabling
NIST
-
https://csrc.nist.gov/pubs/sp/800/53/r5/upd1/final