+Article 54 5.

Article 54 5.

Paragraph 4 shall not apply to fully integrated network components or for the usual depreciation period of new battery storage facilities with a final investment decision until 2024, provided that such battery storage facilities are:

(a) 

connected to the grid at the latest two years thereafter;

(b) 

integrated into the transmission system;

(c) 

used only for the reactive instantaneous restoration of network security in the case of network contingencies where such restoration measure starts immediately and ends when regular re-dispatch can solve the issue; and

(d) 

not used to buy or sell electricity in the electricity markets, including balancing.

1. Vue d’ensemble

,
Intitulé Réglementation

1.1 Références

1.2 Exigences identifiées

1.3 Normes associées

2. Exigences identifiées

Exigences
Source Exigence

3. Normes associées

Normes
Source Exigence