+Article 4 1.

Article 4 1.

A project of common interest shall meet the following general criteria:

(a) 

the project is necessary for at least one of the energy infrastructure priority corridors and areas set out in Annex I;

(b) 

the potential overall benefits of the project, assessed in accordance with the relevant specific criteria in paragraph 3, outweigh its costs, including in the longer term;

(c) 

the project meets any of the following criteria:

(i) 

it involves at least two Member States by directly or indirectly, via interconnection with a third country, crossing the border of two or more Member States;

(ii) 

it is located on the territory of one Member State, either inland or offshore, including islands, and has a significant cross-border impact as set out in point (1) of Annex IV.

1. Áttekintés

,
Megnevezés Szabályozás

1.1 Hivatkozások

1.2 Azonosított követelmények

1.3 Kapcsolódó szabványok

2. Azonosított követelmények

Követelmények
Forrás Követelmény

3. Kapcsolódó szabványok

Szabványok
Forrás Követelmény
  • Builddate: 29.04.2026 00:00:00 -Doknr: CELEX:32022R0869
  • EULAW -

    EN: Legal acts of the European Union from EUR-Lex, https://eur-lex.europa.eu/. © European Union. Re-use is authorised by Decision 2011/833/EU, provided the source is acknowledged; the consolidated texts are licensed under CC BY 4.0 (EUR-Lex legal notice). Divided into sections and converted into the GRCA format, the wording unchanged. Only the legislation published in the Official Journal of the European Union is deemed authentic.

    DE: Rechtsakte der Europäischen Union aus EUR-Lex, https://eur-lex.europa.eu/. © Europäische Union. Weiterverwendung nach Beschluss 2011/833/EU mit Quellenangabe gestattet; die konsolidierten Fassungen stehen unter CC BY 4.0 (Rechtlicher Hinweis von EUR-Lex). In Abschnitte aufgeteilt und in das GRCA-Format umgewandelt, der Wortlaut unverändert. Verbindlich sind allein die im Amtsblatt der Europäischen Union veröffentlichten Rechtsakte.