+Article 3 5.

Article 3 5.

The Commission shall assess the draft national building renovation plans submitted pursuant to paragraph 3, in particular with regard to whether:

(a) 

the level of ambition of the nationally established targets is sufficient and in line with the national commitments on climate and energy laid down in the national integrated energy and climate plans;

(b) 

the policies and measures are sufficient to achieve the nationally established targets;

(c) 

the allocation of budgetary and administrative resources is sufficient for the implementation of the plan;

(d) 

the financing sources and measures referred to in paragraph 2, first subparagraph, point (d), of this Article are in line with the planned reduction of energy poverty referred to in paragraph 2, first subparagraph, point (b), of this Article;

(e) 

the plans prioritise the renovation of worst-performing buildings in accordance with Article 9;

(f) 

the public consultation pursuant to paragraph 4 has been sufficiently inclusive; and

(g) 

the plans comply with the requirements of paragraph 1 and the template in Annex II.

After consulting the Committee established by Article 33 of this Directive, the Commission may issue country-specific recommendations to Member States in accordance with Article 9(2) and Article 34 of Regulation (EU) 2018/1999.

With regard to the first draft national building renovation plan, the Commission may issue country-specific recommendations to Member States no later than six months after the Member State has submitted that plan.

1. Panoramica

,
Titolo Regolamentazione

1.1 Riferimenti

1.2 Requisiti identificati

1.3 Standard correlati

2. Requisiti identificati

Requisiti
Fonte Requisito

3. Standard correlati

Standard
Fonte Requisito