APP.7.A8 Early Involvement of the Process Owner in Development-Related Software Tests (S)

The Process Owner SHOULD be involved in the software developers’ tests early on in the development process (before final acceptance). This SHOULD be agreed in the project schedule in coordination with the contractor from the start.