+Article 11 2.

Article 11 2.

By way of derogation from paragraph 1, for Strategic Projects in the Union that were subject to the permit-granting process before being recognised as Strategic Projects and for extensions of existing Strategic Projects that have already been granted a permit, the duration of the permit-granting process after the project is recognised as a Strategic Project shall not exceed:

(a) 

24 months for Strategic Projects involving extraction;

(b) 

12 months for Strategic Projects involving only processing or recycling.