+Article 16e 2.

Article 16e 2.

Unless there are justified safety concerns, unless further works are needed for grid connections or unless there is technical incompatibility of the system components, Member States shall ensure that connections to the transmission or distribution grid shall be permitted within two weeks of the notification to the relevant entity for:

(a) 

heat pumps of up to 12 kW electrical capacity; and

(b) 

heat pumps of up to 50 kW electrical capacity installed by renewables self-consumers, provided that the electrical capacity of a renewables self-consumer’s renewable electricity generation installation amounts to at least 60 % of the electrical capacity of the heat pump.