+Article 13 3.

Article 13 3.

Non-market-based redispatching of generation, energy storage and demand response may only be used where:

(a) 

no market-based alternative is available;

(b) 

all available market-based resources have been used;

(c) 

the number of available power generating, energy storage or demand response facilities is too low to ensure effective competition in the area where suitable facilities for the provision of the service are located; or

(d) 

the current grid situation leads to congestion in such a regular and predictable way that market-based redispatching would lead to regular strategic bidding which would increase the level of internal congestion and the Member State concerned either has adopted an action plan to address this congestion or ensures that minimum available capacity for cross-zonal trade is in accordance with Article 16(8).

1. Prezentare generală

,
Titlu Reglementare

1.1 Referințe

1.2 Cerințe identificate

1.3 Standarde asociate

2. Cerințe identificate

Cerințe
Sursă Cerință

3. Standarde asociate

Standarde
Sursă Cerință
  • Builddate: 16.07.2024 00:00:00 -Doknr: CELEX:32019R0943
  • EULAW -

    EN: Legal acts of the European Union from EUR-Lex, https://eur-lex.europa.eu/. © European Union. Re-use is authorised by Decision 2011/833/EU, provided the source is acknowledged; the consolidated texts are licensed under CC BY 4.0 (EUR-Lex legal notice). Divided into sections and converted into the GRCA format, the wording unchanged. Only the legislation published in the Official Journal of the European Union is deemed authentic.

    DE: Rechtsakte der Europäischen Union aus EUR-Lex, https://eur-lex.europa.eu/. © Europäische Union. Weiterverwendung nach Beschluss 2011/833/EU mit Quellenangabe gestattet; die konsolidierten Fassungen stehen unter CC BY 4.0 (Rechtlicher Hinweis von EUR-Lex). In Abschnitte aufgeteilt und in das GRCA-Format umgewandelt, der Wortlaut unverändert. Verbindlich sind allein die im Amtsblatt der Europäischen Union veröffentlichten Rechtsakte.