+Article 48 1. |
Article 48 1.The Union-wide network development plan referred to under Article 30(1), point (b), shall include the modelling of the integrated network, including scenario development and an assessment of the resilience of the system. Relevant input parameters for the modelling such as assumptions on fuel and carbon prices or installation of renewables shall be fully consistent with the European resource adequacy assessment developed pursuant to Article 23. The Union-wide network development plan shall, in particular:
(a)
build on national investment plans, taking into account regional investment plans as referred to in Article 34(1) of this Regulation, and, if appropriate, Union aspects of network planning as set out in Regulation (EU) No 347/2013; it shall be subject to a cost-benefit analysis using the methodology established as set out in Article 11 of that Regulation;
(b)
regarding cross-border interconnections, also build on the reasonable needs of different system users and integrate long-term commitments from investors referred to in Articles 44 and 51 of Directive (EU) 2019/944; and
(c)
identify investment gaps, in particular with respect to cross-border capacities. In regard to point (c) of the first subparagraph, a review of barriers to the increase of cross-border capacity of the network arising from different approval procedures or practices may be annexed to the Union–wide network development plan. 1. Prezentare generală
1.1 Referințe1.2 Cerințe identificate1.3 Standarde asociate2. Cerințe identificate
3. Standarde asociate
|