+Article 59 2. |
Article 59 2.The Commission is empowered to adopt delegated acts in accordance with Article 68 supplementing this Regulation with regard to the establishment of network codes in the following areas:
(a)
network connection rules including rules on the connection of transmission-connected demand facilities, transmission-connected distribution facilities and distribution systems, connection of demand units used to provide demand response, requirements for grid connection of generators and other system users, requirements for high-voltage direct current grid connection, requirements for direct current-connected power park modules and remote-end high-voltage direct current converter stations, and operational notification procedures for grid connection;
(b)
data exchange, settlement and transparency rules, including in particular rules on transfer capacities for relevant time horizons, estimates and actual values on the allocation and use of transfer capacities, forecast and actual demand of facilities and aggregation thereof including unavailability of facilities, forecast and actual generation of generation units and aggregation thereof including unavailability of units, availability and use of networks, congestion management measures and balancing market data. Rules should include ways in which the information is published, the timing of publication, the entities responsible for handling;
(c)
third-party access rules;
(d)
operational emergency and restauration procedures in an emergency including system defence plans, restoration plans, market interactions, information exchange and communication and tools and facilities;
(e)
sector-specific rules for cyber security aspects of cross-border electricity flows, including rules on common minimum requirements, planning, monitoring, reporting and crisis management. 1. Översikt
1.1 Referenser1.2 Identifierade krav1.3 Relaterade standarder2. Identifierade krav