+ANNEX
---+1. SUMMARY OF THE ELECTRICITY CRISIS SCENARIOS
---+2. ROLES AND RESPONSIBILITIES OF THE COMPETENT AUTHORITY
---+3. PROCEDURES AND MEASURES IN THE ELECTRICITY CRISIS
------+3.1. National procedures and measures
------+3.2. Regional and bilateral procedures and measures
---+4. CRISIS COORDINATOR
---+5. STAKEHOLDER CONSULTATIONS
---+6. EMERGENCY TESTS

ANNEX

ANNEX

1. Übersicht

,
Bezeichnung Regulierung
1. SUMMARY OF THE ELECTRICITY CRISIS SCENARIOS

1.   SUMMARY OF THE ELECTRICITY CRISIS SCENARIOS

Describe briefly the electricity crisis scenarios identified at regional and national level in accordance with the procedure laid down in Articles 6 and 7, including the description of the assumptions applied.

2. ROLES AND RESPONSIBILITIES OF THE COMPETENT AUTHORITY

2.   ROLES AND RESPONSIBILITIES OF THE COMPETENT AUTHORITY

Define the role and responsibilities of the competent authority and the bodies to which tasks have been delegated.

Describe which tasks, if any, have been delegated to other bodies.

3. PROCEDURES AND MEASURES IN THE ELECTRICITY CRISIS

3.   PROCEDURES AND MEASURES IN THE ELECTRICITY CRISIS

4. CRISIS COORDINATOR

4.   CRISIS COORDINATOR

Indicate and define the role of the crisis coordinator. Specify the contact details.

5. STAKEHOLDER CONSULTATIONS

5.   STAKEHOLDER CONSULTATIONS

In accordance with Article 10(1), describe the mechanism used for and the results of the consultations carried out, for the development of this plan, with:

(a)

relevant electricity and natural gas undertakings, including relevant producers or their trade bodies;

(b)

relevant organisations representing the interests of non-industrial electricity customers;

(c)

relevant organisations representing the interests of industrial electricity customers;

(d)

regulatory authorities;

(e)

the transmission system operators;

(f)

relevant distribution system operators.

6. EMERGENCY TESTS

6.   EMERGENCY TESTS

(a)

Indicate the calendar for the biennial regional (and, if applicable also national) real time response simulations of electricity crises;

(b)

In accordance with point (d) of Article 12(1), indicate procedures agreed and the actors involved.

For the updates of the plan: briefly describe the tests carried out since the last plan was adopted and the main results. Indicate which measures have been adopted as a result of those tests.

1.1 Referenzen

1.2 Identifizierte Anforderungen

1.3 Zugehörige Standards

2. Identifizierte Anforderungen

Anforderungen
Quelle Anforderung

3. Zugehörige Standards

Standards
Quelle Anforderung
  • Builddate: 14.06.2019 00:00:00 -Doknr: CELEX:32019R0941
  • EULAW -

    EN: Legal acts of the European Union from EUR-Lex, https://eur-lex.europa.eu/. © European Union. Re-use is authorised by Decision 2011/833/EU, provided the source is acknowledged; the consolidated texts are licensed under CC BY 4.0 (EUR-Lex legal notice). Divided into sections and converted into the GRCA format, the wording unchanged. Only the legislation published in the Official Journal of the European Union is deemed authentic.

    DE: Rechtsakte der Europäischen Union aus EUR-Lex, https://eur-lex.europa.eu/. © Europäische Union. Weiterverwendung nach Beschluss 2011/833/EU mit Quellenangabe gestattet; die konsolidierten Fassungen stehen unter CC BY 4.0 (Rechtlicher Hinweis von EUR-Lex). In Abschnitte aufgeteilt und in das GRCA-Format umgewandelt, der Wortlaut unverändert. Verbindlich sind allein die im Amtsblatt der Europäischen Union veröffentlichten Rechtsakte.