+INF.2 Data Centre and Server Room
---+INF.2.G1. Incorrect Planning
---+INF.2.G2. Insufficient Site Access Controls
---+INF.2.G3. Insufficient Monitoring
---+INF.2.G4. Insufficient Air Conditioning in a Data Centre
---+INF.2.G5. Fire
---+INF.2.G6. Water
---+INF.2.G7. Insufficient Burglary Protection
---+INF.2.G8. Failure of the Power Supply
---+INF.2.G9. Contamination
---+INF.2.A1 Defining Requirements [Building Services, Planner] (B)
---+INF.2.A2 Formation of Fire Zones [Planner] (B)
---+INF.2.A3 Use of an Uninterruptible Power Supply [Building Services] (B)
---+INF.2.A4 Emergency Shutdown of the Power Supply [Building Services] (B)
---+INF.2.A5 Maintenance of Air Temperature and Humidity [Building Services] (B)
---+INF.2.A6 Site Access Control [Building Services] (B)
---+INF.2.A7 Locking and Securing Facilities [Employee, Building Services] (B)
---+INF.2.A8 Use of a Fire Alarm System [Planner] (B)
---+INF.2.A9 Use of an Extinguishing or Fire Prevention System [Building Services] (B)
---+INF.2.A10 Inspection and Maintenance of Infrastructure [Maintenance Personnel, Building Services] (B)
---+INF.2.A11 Automatic Monitoring of Infrastructure [Building Services] (B)
---+INF.2.A17 Use of Early Fire Detection [Planner, Building Services] (B)
---+INF.2.A29 Avoidance and Monitoring of Unnecessary Wiring [Building Services, Planner] (B)
---+INF.2.A12 Data Centre Perimeter Protection [Planner, Building Services] (S)
---+INF.2.A13 Planning and Installation of Alarm Systems [Building Services] (S)
---+INF.2.A14 Use of an Emergency Power System [Planner, Building Services] (S)
---+INF.2.A15 Overvoltage Protection Devices [Planner, Building Services] (S)
---+INF.2.A16 Air Conditioning in Data Centres [Planner] (S)
---+INF.2.A19 Functional Testing of Technical Infrastructure [Building Services] (S)
---+INF.2.A30 Systems for Extinguishing or Preventing Fires [Building Services, Planner] (S)
---+INF.2.A21 Alternate Data Centre (H)
---+INF.2.A22 Implementation of Dust-Protection Measures [Building Services] (H)
---+INF.2.A23 Appropriate Design of Data Centre Cabling [Building Services] (H)
---+INF.2.A24 Use of Video Monitoring Systems [Data Protection Officer, Building Services, Planner] (H)
---+INF.2.A25 Redundant Design of Uninterruptible Power Supplies [Planner] (H)
---+INF.2.A26 Redundant Design of Emergency Power Systems [Planner] (H)
---+INF.2.A28 Use of Higher-Level Alarm Systems [Planner] (H)

INF.2 Data Centre and Server Room

Introduction

Today, almost all strategic and operative functions and tasks are substantially supported by (if not entirely dependent on) information technology. As a consequence, the requirements for the performance and availability of IT systems and their network connections are constantly increasing. To meet these performance requirements, ensure that adequate reserve capacity is available, and operate IT in economical ways, organisations of all sizes concentrate their IT landscapes in data centres.

A data centre is defined as follows:

  • If an organisation that uses IT has only one central area of IT operations, this, together with the required support areas, must generally always be treated as a data centre in terms of its protection needs. The term “area of IT operations” refers to rooms in which hardware is installed and operated to provide services and data. In addition to its area of IT operations, a data centre comprises all other technical support areas (e.g. power supply, cold air supply, extinguishing technology, security technology) that facilitate the correct operation and security of the area of IT operations.
  • If an organisation’s IT operations are distributed over several areas within a building or a given premises and these areas are connected both to one another and to IT users by internal LAN connections, the most functionally significant of these areas (at minimum) must be treated as a data centre. In addition, areas in which proper operations are crucial for 50% or more of the users at hand or from which 50% or more of the services and data (proportionate to all areas) are provided must be treated as a data centre.
  • If an organisation that uses IT is located at several physically separate sites and these are connected to each other by means other than internal LAN connections, each of the sites must be considered and treated separately according to (1) above.
  • An area of IT operations that houses IT required for critical business processes (i.e. processes whose disruption or failure would significantly impair the fulfilment of an organisation’s primary tasks) must always be treated as a data centre, independent of the size or the proportion specified in (2) above.
  • Areas of IT operations from which services for third parties are performed must always be treated as part of a data centre. Here, it is irrelevant whether these services are subject to fees.
  • If there is a justifiable interest in treating an area of IT operations (together with its support areas) as a server room contrary to the above regulations, reasons must be provided for the resulting reduction of security requirements.

An area does not need to fulfil all six of the points listed here to be considered a data centre. The list merely describes different scenarios in which an area is to be considered a data centre. If an area of IT operations deviates from these definitions, it is referred to as a server room. This designation is solely based on how significant the IT structure in question is to the respective organisation's ability to fulfil its tasks, and thus corresponds to the methodology specified in DIN EN 50600.

If a server room is to be protected, the requirements in this module can be reduced accordingly. However, substantial and comprehensible reasons must be given for this in accordance with (6) above and the Basic Requirements must be implemented at minimum.

Objective

On the one hand, this module is directed towards organisations that operate a data centre and want to check if suitable security safeguards have been implemented in the framework of an audit. On the other, the module can also be used to estimate the security safeguards that will need to be implemented if IT is to be centralised in a data centre. The primary goal of the requirements described in this module is to ensure the secure operation of data centres.

Scoping and Modelling

INF.2 Data Centre and Server Room must be applied to every data centre and every server room.

It is not suitable for small information domains with, for example, only one or a very small number of servers or IT systems. This might involve a small organisation with a few IT workstations and a server that is located in a separate room, for example. In such cases, it is often sufficient to implement module INF.5 Room or Cabinet for Technical Infrastructure.

General requirements for buildings and cabling are also not part of this module. These can be found in the modules INF.1 Generic Building and INF.12 Cabling.

To make this module easier to understand, technical details and planning variables have deliberately been avoided. The relevant standards and other BSI publications provide more detailed information.

Useful Resources

The BSI makes the documents “Redundanz Modularität Skalierbarkeit” [Redundancy, Modularity, Scalability] and “Kriterien für die Standortwahl von Rechenzentren” [Criteria for the Siting of Data Centres] available on its website.

The German Institute for Standardisation (DIN) describes general principles for the design of data centres in the standard DIN EN 50600-1:2019-08, "Information Technology – Data Centre Facilities and Infrastructures – Part 1: General Concepts”.

The German Institute for Standardisation (DIN) deals with the topic of lightning protection in the standard DIN EN 62305-4:2011-10, "Protection Against Lightning – Part 4: Electrical and Electronic Systems Within Structures”.

Germany's digital association, Bitkom, provides assistance in planning and setting up a data centre in its guide "Betriebssicheres Rechenzentrum” [Reliable Data Centre].

The German Insurance Association (GDV) describes perimeter security safeguards in the publication “Sicherungsleitfaden Perimeter” [Perimeter Security Guide], which can be used as an aid in securing properties.

1. Übersicht

Bezeichnung Standard
INF.2.A1 Defining Requirements [Building Services, Planner] (B)

Adequate technical and organisational requirements MUST be defined and implemented for a data centre.

When planning a data centre or choosing suitable rooms, appropriate security safeguards MUST also be planned that take the protection needs of the IT components (especially regarding their availability) into account.

A data centre as a whole MUST be designed as a closed security area. In addition, it MUST have different security zones. For example, administration, logistics, and IT operations and support areas MUST be clearly separated from each other. In the case of a server room, it SHOULD be checked whether it is possible to implement different security zones.

INF.2.A2 Formation of Fire Zones [Planner] (B)

Suitable fire and smoke zones MUST be defined for the rooms of a data centre. The fire and smoke zones MUST also provide protection that goes beyond the scope prescribed by building law for the technical equipment located therein and its availability. Fire and smoke MUST be prevented from spreading. In the case of a server room, it SHOULD be checked whether adequate fire and zones can be implemented.

INF.2.A3 Use of an Uninterruptible Power Supply [Building Services] (B)

An uninterruptible power supply (UPS) MUST be installed for all the operationally relevant components of a data centre. As the power consumption of air conditioning is often too high for a UPS, the control of these systems MUST at least be connected to the UPS. In the case of a server room, the necessity of operating a UPS SHOULD be checked based on the availability requirements of the IT systems at hand.

The UPS MUST have sufficient capacity. If there are relevant changes in loads, checks MUST be carried out to establish whether the capacity of the existing UPS systems is still sufficient.

In UPS systems that use a battery for energy storage, the battery MUST be kept within the required temperature range. For this purpose, it SHOULD be kept away from the power electronics of the UPS if possible. The UPS MUST be serviced and checked for functionality at regular intervals. The maintenance schedule specified by the manufacturer MUST be followed for this purpose.

INF.2.A4 Emergency Shutdown of the Power Supply [Building Services] (B)

There MUST be suitable options for switching off the electrical consumers in a data centre. Attention MUST be paid to whether and how an existing UPS is spatially and functionally integrated into the power supply. If conventional emergency stop switches are used, it MUST be ensured that the entire data centre will not be switched off. The emergency shutdown system MUST be subdivided in a systematic and sensible manner. All emergency off switches MUST be protected such that they cannot be activated unintentionally or without authorisation.

INF.2.A5 Maintenance of Air Temperature and Humidity [Building Services] (B)

It MUST be ensured that the air temperature and humidity in an IT operating area will remain within the prescribed limits. The actual thermal load in cooled areas MUST be checked at regular intervals and after major conversions.

Any air conditioning systems in use MUST be maintained regularly. At minimum, temperature and humidity parameters MUST be recorded in a way that makes it possible to retrospectively identify whether thresholds have been exceeded as a means of both pinpointing and eliminating the cause of any deviation.

INF.2.A6 Site Access Control [Building Services] (B)

Access to a data centre MUST be controlled. Site access rights MUST be assigned in accordance with the specifications of module ORP.4 Identity and Access Management. It MUST be ensured that those who work at a data centre do not have access to IT systems outside their scope of work.

All the possible ways to access a data centre MUST be equipped with site access control devices. Each instance in which a person accesses a data centre MUST be individually recorded by a site access control system. In the case of a server room, it SHOULD be checked whether it is appropriate to monitor all the possible ways to access the site in question.

Regular checks MUST be carried out to determine whether the regulations regarding the use of site access controls are being observed.

An organisation's requirements regarding its site access control system MUST be documented in a concept with a sufficient level of detail.

INF.2.A7 Locking and Securing Facilities [Employee, Building Services] (B)

All the doors of a data centre MUST always be kept locked. Windows MUST be avoided in the planning stage whenever possible. If there are windows, they MUST always be kept locked. Doors and windows MUST provide protection adequate for the security level at hand against attacks and external influences. They MUST have privacy screens. Consideration MUST be given to the structural design of all room-forming elements and their ability to provide a uniform level of protection.

INF.2.A8 Use of a Fire Alarm System [Planner] (B)

A fire alarm system MUST be installed in a data centre. It MUST monitor all areas. All the alarms of the fire alarm system MUST be forwarded appropriately (see also INF.2.A13 Planning and Installation of Alarm Systems). The fire alarm system MUST be serviced at regular intervals. It MUST be ensured that no particular fire loads are present in the rooms of a data centre.

INF.2.A9 Use of an Extinguishing or Fire Prevention System [Building Services] (B)

An extinguishing or fire prevention system in line with the current state of the art MUST be installed in a data centre. If this is not possible, technical (especially a wide-area early detection system; see INF.2.A17 Early Fire Detection) and organisational measures (trained personnel and response plans for early fire detection alarms) MUST ensure that early fire detection alarms are responded to immediately and within no more than three minutes.

In server rooms without an extinguishing or fire prevention system, hand-held fire extinguishers with suitable extinguishing agents MUST be available in sufficient number and size. Attention MUST be paid to the fact that these provisions do not affect any additional building code requirements regarding the provision of hand-held fire extinguishers. The fire extinguishers MUST be mounted so that they are easy to access in case of a fire. Each fire extinguisher must be inspected and serviced regularly. All staff who are allowed to enter a data centre or server room MUST be instructed in the use of hand-held fire extinguishers.

INF.2.A10 Inspection and Maintenance of Infrastructure [Maintenance Personnel, Building Services] (B)

For all components of building services infrastructure, the intervals and requirements for inspection and maintenance recommended by the respective manufacturers or specified by corresponding standards MUST be observed at minimum. Inspections and maintenance work MUST be documented. Firestop seals MUST be checked to ensure that they are intact. The results MUST be documented.

INF.2.A11 Automatic Monitoring of Infrastructure [Building Services] (B)

All infrastructure facilities, including leakage monitoring, air conditioning, and power and UPS systems, MUST be automatically monitored. Detected disruptions MUST be reported and dealt with in an appropriate manner as quickly as possible.

In the case of a server room, IT and support devices that do not or only occasionally need to be operated by a person SHOULD be equipped with a remote means of indicating malfunctions. The responsible employees MUST be alerted promptly.

INF.2.A17 Use of Early Fire Detection [Planner, Building Services] (B)

A data centre MUST be equipped with an early fire detection system. A server room SHOULD be equipped with an early fire detection system. Early fire detection alarms MUST be routed to a continuously staffed department that can initiate a corresponding check and a protective response within three minutes. Alternatively, an automatic protective response MUST be initiated. In order to achieve a balance between fire protection and availability, it MUST be ensured that equipment providing redundancy is not located together within the effective range of the same voltage isolation circuit.

INF.2.A29 Avoidance and Monitoring of Unnecessary Wiring [Building Services, Planner] (B)

The cables laid in a data centre MUST be restricted to those that directly supply the technology installed there (usually IT and, if applicable, cooling technology). If structural reasons make it unavoidable to run lines through a data centre in order to supply areas other than those within the data centre, this MUST be documented along with suitable justification. The risks posed by such lines MUST be minimised by appropriate safeguards (e.g. enclosures and monitoring).

The aforementioned lines may be routed through server rooms without justifying why this is unavoidable, but they MUST be treated in the same way as described for data centres.

Messages from systems that monitor such lines MUST be checked and evaluated immediately to determine whether a threat is present. Countermeasures MUST be implemented in a timely manner according to the threat level identified (see also INF.2.A13 Planning and Installation of Alarm Systems).

INF.2.A12 Data Centre Perimeter Protection [Planner, Building Services] (S)

Perimeter protection SHOULD be in place for data centres. Depending on the protection needs defined for a given data centre and its premises, perimeter protection SHOULD consist of the following components:

  • A wall or fence around the property
  • Security safeguards against accidental trespassing (crossing the property line)
  • Security safeguards against deliberate trespassing without the use of force
  • Security safeguards against deliberate trespassing through the use of force
  • Outdoor security safeguards
  • Visual detection of people and vehicles
  • Safeguards for preserving evidence (e.g. video recording)
  • Automatic alerts
INF.2.A13 Planning and Installation of Alarm Systems [Building Services] (S)

The corresponding building's security concept SHOULD be used to plan which alarm systems are needed and should be installed for specific areas of a data centre. In addition, a procedure for dealing with alarm messages SHOULD be defined. The security concept SHOULD always be adapted if and when the use of the building's areas changes.

An alarm system that is fit for purpose SHOULD be installed. The notifications from the alarm system SHOULD be transmitted to an alarm receiving centre in compliance with the applicable technical connection requirements. The selected alarm receiving centre MUST be reachable at all times. It MUST be able to react appropriately to alarms in terms of its technology and personnel. The transmission path between the alarm system and the alarm receiving centre SHOULD be designed according to the technical connection requirements at hand and, if possible, with redundancy. All established transmission routes MUST be tested at regular intervals.

INF.2.A14 Use of an Emergency Power System [Planner, Building Services] (S)

The power supplied to a data centre from the grid of an energy utility company SHOULD be supplemented by an emergency power system (EPS). If an EPS is in place, it MUST be regularly maintained. Load and functional tests, as well as test runs under load, MUST be conducted when performing maintenance.

The operating supplies for an EPS MUST be checked regularly to see if they are sufficient. Regular checks MUST also be performed to ensure that these supplies are still usable, and especially to avoid "diesel bug". If possible, low-sulphur heating oil SHOULD be used instead of diesel fuel. Refuelling operations MUST be logged. The log MUST include the type of fuel, the additives used, the date of refuelling, and the quantity refuelled.

If an EPS is not used for a server room, a UPS with a run time appropriate for the protection needs at hand SHOULD be implemented as an alternative.

INF.2.A15 Overvoltage Protection Devices [Planner, Building Services] (S)

A lightning and overvoltage protection concept SHOULD be drawn up on the basis of the currently valid standard (DIN EN 62305 parts 1 to 4). The lightning protection zones (LPZ) required for the proper operation of a data centre must be defined. For all the facilities required for the proper operation of a data centre and its ability to provide services, this SHOULD be at least LPZ 2. All overvoltage protection equipment SHOULD be subject to a comprehensive test once a year in accordance with DIN EN 62305-3 (table E.2).

INF.2.A16 Air Conditioning in Data Centres [Planner] (S)

It SHOULD be ensured that suitable climatic conditions are established and maintained in a data centre. A data centre's air-conditioning system SHOULD have sufficient capacity. All the relevant values SHOULD be constantly monitored. If a value deviates from the norm, an automatic alarm SHOULD be triggered.

Air-conditioning systems SHOULD be as fail-safe as possible in areas of IT operations.

INF.2.A19 Functional Testing of Technical Infrastructure [Building Services] (S)

The technical infrastructure of a data centre SHOULD be tested regularly (at least once or twice a year) and following system modifications and extensive repairs. The results SHOULD be documented. In particular, entire reaction chains SHOULD be subjected to a real function test.

INF.2.A30 Systems for Extinguishing or Preventing Fires [Building Services, Planner] (S)

A data centre SHOULD be equipped with an automatic extinguishing or fire prevention system.

INF.2.A21 Alternate Data Centre (H)

A geographically separate alternate data centre SHOULD be established. The alternate data centre SHOULD have sufficient capacity to maintain all of the corresponding organisation’s processes. It SHOULD always be ready for operation, as well. All of the organisation’s data SHOULD be mirrored to the alternate data centre on a regular basis. The procedure for switching to the emergency data centre SHOULD be tested and drilled regularly. The transmission routes to the alternate data centre SHOULD be suitably secured and designed with appropriate redundancy.

INF.2.A22 Implementation of Dust-Protection Measures [Building Services] (H)

During construction work in a data centre, suitable dust-protection measures SHOULD be defined, planned, and implemented. Persons who are not involved in the construction work themselves SHOULD check the dust-protection measures frequently to make sure they are working properly and the regulations on dust protection are being followed.

INF.2.A23 Appropriate Design of Data Centre Cabling [Building Services] (H)

Cable routes in data centres SHOULD be carefully planned and implemented. Cable trays in data centres SHOULD be carefully designed in terms of their arrangement and dimensioning so that separation of voltage levels and a sensible distribution of cables on the trays is possible, and that sufficient space is also available for future increases in demand. To ensure the optimal supply of IT hardware that has two power supply units, a two-line A-B supply SHOULD be set up from the low-voltage main distributor for the IT operating areas in question. Pairs of redundant lines SHOULD be laid in separate trays.

INF.2.A24 Use of Video Monitoring Systems [Data Protection Officer, Building Services, Planner] (H)

Site access control and intrusion detection systems SHOULD be supplemented by video monitoring systems. A video monitoring system SHOULD be integrated into the overall security concept at hand. The Data Protection Officer MUST always be involved in the planning, design, and potential evaluation of video recordings.

The central technical components required for a video monitoring system SHOULD be installed in a suitable environment and protected. The video monitoring system SHOULD be tested regularly to ensure its proper function and its compliance with the angles of view agreed with the Data Protection Officer.

INF.2.A25 Redundant Design of Uninterruptible Power Supplies [Planner] (H)

UPS systems SHOULD be modular and designed to have a redundant module compensate for any failure without interruption. If a two-line A-B supply is set up for IT operating areas, each of the two current paths SHOULD be equipped with an independent UPS system.

INF.2.A26 Redundant Design of Emergency Power Systems [Planner] (H)

Emergency power systems SHOULD be redundant. With regard to maintenance, a redundant EPS MUST also be treated according to INF.2.A14 Use of an Emergency Power System.

INF.2.A28 Use of Higher-Level Alarm Systems [Planner] (H)

For areas of data centres with increased protection needs, VdS class-C alarm systems SHOULD be used exclusively (in line with VdS Guideline 2311).

1.1 Referenzen

1.2 Identifizierte Anforderungen

1.3 Zugehörige Regulierungen

2. Identifizierte Anforderungen

Anforderungen
Quelle Anforderung

3. Zugehörige Regulierungen

Regulierungen
Quelle Regulierung

Verknüpfte Vorgänge