+INF.2.A4 Emergency Shutdown of the Power Supply [Building Services] (B)
|
INF.2.A4 Emergency Shutdown of the Power Supply [Building Services] (B)
There MUST be suitable options for switching off the electrical consumers in a data centre. Attention MUST be paid to whether and how an existing UPS is spatially and functionally integrated into the power supply. If conventional emergency stop switches are used, it MUST be ensured that the entire data centre will not be switched off. The emergency shutdown system MUST be subdivided in a systematic and sensible manner. All emergency off switches MUST be protected such that they cannot be activated unintentionally or without authorisation.
1. Übersicht
1.1 Referenzen
1.2 Identifizierte Anforderungen
1.3 Zugehörige Regulierungen
2. Identifizierte Anforderungen
Anforderungen
| Quelle |
Anforderung |
3. Zugehörige Regulierungen
Regulierungen
| Quelle |
Regulierung |
Verknüpfte Vorgänge
|