+DER.2.3.A6 Returning to Production Operations (B)

DER.2.3.A6 Returning to Production Operations (B)

After the affected network has been cleaned successfully, the IT systems MUST be returned to production operations in a controlled manner. In so doing, all the previously used IT systems and installed programs that were used to observe and analyse the attack MUST either be removed or incorporated into the productive environment. The same MUST be done with communication and collaboration systems procured for the purpose of cleaning. Evidence and decommissioned IT systems MUST either be deleted or destroyed securely, or archived appropriately.

1. Übersicht

Bezeichnung Standard

1.1 Referenzen

1.2 Identifizierte Anforderungen

1.3 Zugehörige Regulierungen

2. Identifizierte Anforderungen

Anforderungen
Quelle Anforderung

3. Zugehörige Regulierungen

Regulierungen
Quelle Regulierung

Verknüpfte Vorgänge