+INF.2.A15 Overvoltage Protection Devices [Planner, Building Services] (S)

INF.2.A15 Overvoltage Protection Devices [Planner, Building Services] (S)

A lightning and overvoltage protection concept SHOULD be drawn up on the basis of the currently valid standard (DIN EN 62305 parts 1 to 4). The lightning protection zones (LPZ) required for the proper operation of a data centre must be defined. For all the facilities required for the proper operation of a data centre and its ability to provide services, this SHOULD be at least LPZ 2. All overvoltage protection equipment SHOULD be subject to a comprehensive test once a year in accordance with DIN EN 62305-3 (table E.2).

1. Overview

Summary Standard

1.1 References

1.2 Identified Requirements

1.3 Related Regulations

2. Identified Requirements

Requirements
Source Requirement

3. Related Regulations

Regulations
Source Regulation