+Article 10 1.
|
Article 10 1.
The permit granting process shall consist of two procedures:
(a)
the pre-application procedure, covering the period between the start of the permit granting process and the acceptance of the submitted application file by the national competent authority, which shall take place within an indicative period of 24 months; and
(b)
the statutory permit granting procedure, covering the period from the date of acceptance of the submitted application file until the taking of the comprehensive decision, which shall not exceed 18 months.
With regard to point (b) of the first subparagraph, where appropriate, Member States may provide for a statutory permit granting procedure that is shorter than 18 months.
1. Áttekintés
1.1 Hivatkozások
1.2 Azonosított követelmények
1.3 Kapcsolódó szabványok
2. Azonosított követelmények
Követelmények
| Forrás |
Követelmény |
3. Kapcsolódó szabványok
Szabványok
| Forrás |
Követelmény |
- Builddate: 29.04.2026 00:00:00 -Doknr: CELEX:32022R0869
- EULAW -
EN: Legal acts of the European Union from EUR-Lex, https://eur-lex.europa.eu/. © European Union. Re-use is authorised by Decision 2011/833/EU, provided the source is acknowledged; the consolidated texts are licensed under CC BY 4.0 (EUR-Lex legal notice). Divided into sections and converted into the GRCA format, the wording unchanged. Only the legislation published in the Official Journal of the European Union is deemed authentic.
DE: Rechtsakte der Europäischen Union aus EUR-Lex, https://eur-lex.europa.eu/. © Europäische Union. Weiterverwendung nach Beschluss 2011/833/EU mit Quellenangabe gestattet; die konsolidierten Fassungen stehen unter CC BY 4.0 (Rechtlicher Hinweis von EUR-Lex). In Abschnitte aufgeteilt und in das GRCA-Format umgewandelt, der Wortlaut unverändert. Verbindlich sind allein die im Amtsblatt der Europäischen Union veröffentlichten Rechtsakte.
|