+ANNEX V |
ANNEX V
ANNEX V Template for the national risk assessment General information Name of the competent authority responsible for the preparation of the present risk assessment ( 13 ). 1. Description of the system
2. Infrastructure standard (Article 5) Describe how the infrastructure standard is complied with, including the main values used for the N – 1 formula and alternative options for its compliance (with directly connected Member States, demand-side measures) and the existing bidirectional capacities, as follows:
(a)
N – 1 formula
(i)
the identification of the single largest gas infrastructure;
(ii)
the calculation of the N – 1 formula at national level;
(iii)
a description of the values used for all elements in the N – 1 formula, including intermediate values used for their calculation (e.g. for EPm indicate the capacity of all entry points considered under this parameter);
(iv)
an indication of the methodologies used, if any, for the calculation of parameters in the N – 1 formula (e.g. Dmax) (use annexes for detailed explanations);
(v)
an explanation of the results of the calculation of the N – 1 formula considering the level of storages at 30 % and 100 % of the maximum working volume;
(vi)
an explanation of the main results of the simulation of the N – 1 formula using a hydraulic model;
(vii)
if so decided by the Member State, a calculation of the N – 1 formula using demand-side measures:
—
calculation of the N – 1 formula in accordance with point 2 of Annex II,
—
description of the values used for all elements in the N – 1 formula, including intermediate figures used for the calculation (if different to the figures described under point 2(a)(iii)),
—
indicate the methodologies used, if any, for the calculation of parameters in the N – 1 formula (e.g. Dmax) (use annexes for detailed explanations),
—
explain the market-based demand-side measures adopted/to be adopted to compensate a disruption of gas supply and its expected impact (Deff);
(viii)
if so agreed with the competent authorities of the relevant risk group(s) or with directly connected Member States, joint calculation(s) of the N – 1 formula:
—
calculation of the N – 1 formula in accordance with point 5 of Annex II,
—
description of the values used for all elements in the N – 1 formula, including intermediate values used for their calculation (if different to the figures described under point 2(a)(iii)),
—
indicate the methodologies and assumptions used, if any, for the calculation of parameters in the N – 1 formula (e.g. Dmax) (use annexes for detailed explanations),
—
explain the agreed arrangements to ensure compliance with the N – 1 formula;
(b)
bi-directional capacity
(i)
indicate the interconnection points equipped with bidirectional capacity and the maximal capacity of bi-directional flows;
(ii)
indicate the arrangements governing the use of the reverse flow capacity (e.g. interruptible capacity);
(iii)
indicate interconnection points where an exemption has been granted in accordance with Article 5(4), the duration of the exemption and the grounds on which it was granted. 3. Identification of risks Describe the risk factors which could have negative impact on the security of gas supply in the Member State, their likelihood and consequences. Non-exhaustive list of types of risk factors that have to be included in the assessment only if applicable according to the competent authority:
(a)
political
—
gas disruption from third countries because of different reasons,
—
political unrest (either in country of origin or in transit country),
—
war/civil war (either in country of origin or in transit country),
—
terrorism;
(b)
technological
—
explosion/fires,
—
fires (internal to a given facility),
—
leakages,
—
lack of adequate maintenance,
—
equipment malfunction (failure to start, failure during working time, etc.),
—
lack of electricity (or other energy source),
—
ICT failure (hardware or software failure, internet, SCADA problems, etc.),
—
cyber-attack,
—
impact due to excavation works (digging, piling), ground works, etc.;
(c)
commercial/market/financial
—
agreements with third-country suppliers,
—
commercial dispute,
—
control of infrastructure relevant for the security of gas supply by third-country entities, which may imply, among others, risks of underinvestment, undermining diversification or non-respect of Union law,
—
price volatility,
—
underinvestment,
—
sudden, unexpected peak demand,
—
other risks which could lead to structural underperformance;
(d)
social
—
strikes (in different related sectors, such as the gas sector, ports, transport, etc.),
—
sabotage,
—
vandalism,
—
theft;
(e)
natural
—
earthquakes,
—
landslides,
—
floods (heavy rain, river),
—
storms (sea),
—
avalanches,
—
extreme weather conditions,
—
fires (external to the facility, like nearby forests, grassland, etc.).
Analysis
(a)
identify the relevant risk factors for the Member State, including their likelihood and impact;
(b)
describe the criteria used to determine whether a system is exposed to high/unacceptable risks;
(c)
set a list of relevant risk scenarios in accordance with the risk factors and their likelihood and describe how the selection was made. 4. Risk analysis and assessment Analyse the set of relevant risk scenarios identified under point 3. In the simulation of risk scenarios include the existing security of gas supply measures, such as the infrastructure standard calculated using the N – 1 formula as set out in point 2 of Annex II, and the gas supply standard. Per risk scenario:
(a)
describe in detail the risk scenario, including all assumptions and, if applicable, the underlying methodologies for their calculation;
(b)
describe in detail the results of the simulation carried out, including a quantification of the impact (e.g. volumes of unserved gas, the socioeconomic impact, the impact on district heating, the impact on electricity generation). 5. Conclusions Describe the main results of the common risk assessment the Member States has been involved in, including the identification of risk scenarios that require further action. 1. Apžvalga