2. The Commission shall, after consulting the ECG, issue a non-binding opinion, setting out detailed reasons, and submit it to the competent authority, with a recommendation to review its risk-preparedness plan where that plan:
|
(a)
|
is not effective to mitigate the risks identified in the electricity crisis scenarios;
|
|
(b)
|
is inconsistent with the electricity crisis scenarios identified or with the risk-preparedness plan of another Member State;
|
|
(c)
|
does not comply with the requirements laid down in Article 10(2);
|
|
(d)
|
sets out measures that are likely to jeopardise the security of electricity supply of other Member States;
|
|
(e)
|
unduly distorts competition or the effective functioning of the internal market; or
|
|
(f)
|
does not comply with the provisions of this Regulation or other provisions of Union law.
|