+INF.14.A2 Defining Commissioning and Interface Management for BACS (B)

INF.14.A2 Defining Commissioning and Interface Management for BACS (B)

Due to the large number of building services systems and building components that are connected in BACS, the commissioning procedure for the building services systems and BACS-relevant components involved MUST be coordinated and defined across the multiple areas at hand. This process MUST be implemented in a coordinated manner to ensure a fully functional building.

Clear interfaces MUST also be defined between the operator organisations of the BACS and the BACS-relevant components, as well as between the operator organisations of the building services systems.

Commissioning and interface management MUST be documented. The specifications MUST be checked and readjusted both regularly and whenever required. In particular, the specifications must be adapted in case of changes within the BACS.

1. Overzicht

Titel Standaard

1.1 Referenties

1.2 Geïdentificeerde eisen

1.3 Gerelateerde regelingen

2. Geïdentificeerde eisen

Eisen
Bron Eis

3. Gerelateerde regelingen

Regelingen
Bron Regelgeving

Gekoppelde issues

Koppelingen
Koppelingstype Issue
blocks G 0.18 Poor Planning or Lack of Adaptation