+Člen 17 Obveznosti ob in po zaprtju
---+Article 17 1.
---+Article 17 2.
---+Article 17 3.
---+Article 17 4.
---+Article 17 5.

Člen 17 Obveznosti ob in po zaprtju

Člen 17

Obveznosti ob in po zaprtju

1.  Območje shranjevanja se zapre:

(a) če so izpolnjeni pogoji iz dovoljenja;

(b) na vsebinsko utemeljeno zahtevo upravljavca po odobritvi pristojnega organa; ali

(c) če se pristojni organ tako odloči po odvzemu dovoljenja za shranjevanje v skladu s členom 11(3).

2.  Po zaprtju območja shranjevanja v skladu s točkama (a) ali (b) odstavka 1 je upravljavec še naprej odgovoren za nadzor, poročanje in popravne ukrepe v skladu z zahtevami iz te direktive ter za vse obveznosti v zvezi s prenosom emisijskih kuponov v primeru uhajanja v skladu z Direktivo 2003/87/ES ter za preventivne in sanacijske ukrepe v skladu s členi 5 do 8 Direktive 2004/35/ES, in sicer vse dokler se odgovornost za območje shranjevanja v skladu s členom 18(1) do (5) te direktive ne prenese na pristojni organ. Upravljavec je odgovoren tudi za zapečatenje območja shranjevanja in odstranitev naprav za vbrizgavanje.

3.  Obveznosti iz odstavka 2 se izpolnijo na podlagi načrta za obdobje po zaprtju, ki ga oblikuje upravljavec na podlagi najboljše prakse in v skladu z zahtevami iz Priloge II. Začasni načrt za obdobje po zaprtju se predloži pristojnemu organu, ki ga potrdi v skladu s točko 8 člena 7 in točko 7 člena 9. Pred zaprtjem območja shranjevanja v skladu s točkama (a) in (b) odstavka 1 tega člena se začasni načrt za obdobje po zaprtju:

(a) po potrebi posodobi ob upoštevanju analize tveganja, najboljše prakse in tehnoloških izboljšav;

(b) predloži pristojnemu organu v potrditev; in

(c) potrdi pri pristojnem organu kot končni načrt za obdobje po zaprtju.

4.  Po zaprtju območja shranjevanja v skladu s točko (c) odstavka 1 je pristojni organ odgovoren za nadzor in popravne ukrepe v skladu z zahtevami te direktive in tudi za vse obveznosti v zvezi s prenosom emisijskih kuponov v primeru uhajanja v skladu z Direktivo 2003/87/ES ter za preventivne in sanacijske ukrepe v skladu s členoma 5(1) in 6(1) Direktive 2004/35/ES. Zahteve za obdobje po zaprtju v skladu s to direktivo izpolni pristojni organ na podlagi začasnega načrta za obdobje po zaprtju iz odstavka 3 tega člena, ki se po potrebi posodablja.

5.  Pristojni organ od upravljavca zahteva povrnitev stroškov, nastalih v zvezi z ukrepi iz odstavka 4, vključno z uporabo finančnega jamstva v skladu s členom 19.

1. Pregled

,
Naslov Regulativa
Article 17 1.

A storage site shall be closed:

(a) 

if the relevant conditions stated in the permit have been met;

(b) 

at the substantiated request of the operator, after authorisation of the competent authority; or

(c) 

if the competent authority so decides after the withdrawal of a storage permit pursuant to Article 11(3).

Article 17 2.
After a storage site has been closed pursuant to points (a) or (b) of paragraph 1, the operator remains responsible for monitoring, reporting and corrective measures, pursuant to the requirements laid down in this Directive, and for all obligations relating to the surrender of allowances in case of leakages pursuant to Directive 2003/87/EC and preventive and remedial actions pursuant to Articles 5 to 8 of Directive 2004/35/EC until the responsibility for the storage site is transferred to the competent authority pursuant to Article 18(1) to (5) of this Directive. The operator shall also be responsible for sealing the storage site and removing the injection facilities.
Article 17 3.

The obligations referred to in paragraph 2 shall be fulfilled on the basis of a post-closure plan designed by the operator based on best practice and in accordance with the requirements laid down in Annex II. A provisional post-closure plan shall be submitted to and approved by the competent authority pursuant to Article 7(8) and Article 9(7). Prior to the closure of a storage site pursuant to points (a) or (b) of paragraph 1 of this Article, the provisional post-closure plan shall be:

(a) 

updated as necessary, taking account of risk analysis, best practice and technological improvements;

(b) 

submitted to the competent authority for its approval; and

(c) 

approved by the competent authority as the definitive post-closure plan.

Article 17 4.
After a storage site has been closed pursuant to paragraph 1(c), the competent authority shall be responsible for monitoring and corrective measures pursuant to the requirements laid down in this Directive and for all obligations relating to the surrender of allowances in case of leakages pursuant to Directive 2003/87/EC and preventive and remedial action pursuant to Articles 5(1) and 6(1) of Directive 2004/35/EC. The post-closure requirements pursuant to this Directive shall be fulfilled by the competent authority on the basis of the provisional post-closure plan referred to in paragraph 3 of this Article, which shall be updated as necessary.
Article 17 5.
The competent authority shall recover from the operator the costs incurred in relation to the measures referred to in paragraph 4, including by drawing on the financial security pursuant to Article 19.

1.1 Sklici

1.2 Ugotovljene zahteve

1.3 Povezani standardi

2. Ugotovljene zahteve

Zahteve
Vir Zahteva

3. Povezani standardi

Standardi
Vir Zahteva
  • Builddate: 24.12.2018 00:00:00 -Doknr: CELEX:32009L0031
  • EULAW -

    EN: Legal acts of the European Union from EUR-Lex, https://eur-lex.europa.eu/. © European Union. Re-use is authorised by Decision 2011/833/EU, provided the source is acknowledged; the consolidated texts are licensed under CC BY 4.0 (EUR-Lex legal notice). Divided into sections and converted into the GRCA format, the wording unchanged. Only the legislation published in the Official Journal of the European Union is deemed authentic.

    DE: Rechtsakte der Europäischen Union aus EUR-Lex, https://eur-lex.europa.eu/. © Europäische Union. Weiterverwendung nach Beschluss 2011/833/EU mit Quellenangabe gestattet; die konsolidierten Fassungen stehen unter CC BY 4.0 (Rechtlicher Hinweis von EUR-Lex). In Abschnitte aufgeteilt und in das GRCA-Format umgewandelt, der Wortlaut unverändert. Verbindlich sind allein die im Amtsblatt der Europäischen Union veröffentlichten Rechtsakte.