+DER.3.2.A7 Performance of an IS Audit [IS Audit Team] (B)

DER.3.2.A7 Performance of an IS Audit [IS Audit Team] (B)

Within the framework of an IS audit, the IS Audit Team MUST perform a document audit and an on-site audit. All the results of the two audits MUST be documented in writing and summarised in an IS audit report.

Before performing an IS cross-cutting audit for the first time, the person in charge of the IS audit MUST select an IS partial audit as the IS audit procedure. The IS partial audit MUST be completed with a positive result before an IS cross-cutting audit is performed.

1. Pregled

Naslov Standard

1.1 Reference

1.2 Utvrđeni zahtjevi

1.3 Povezani propisi

2. Utvrđeni zahtjevi

Zahtjevi
Izvor Zahtjev

3. Povezani propisi

Propisi
Izvor Regulativa

Povezani zadaci

Poveznice
Vrsta poveznice Zadatak
blocks G 0.18 Poor Planning or Lack of Adaptation