1.  Finančni okvir za izvajanje EEPO za leti 2009 in 2010 je 3 980 000 000 EUR, ki se dodelijo za:

(a) projekte plinske in električne infrastrukture: 2 365 000 000 EUR;

(b) projekte pridobivanja energije iz vetrnih elektrarn na morju: 565 000 000 EUR;

(c) projekte za zajemanje in skladiščenje CO2: 1 050 000 000 EUR.

▼M1

2.  Posamezne pravne zaveze v skladu s poglavjem II za izvedbo proračunskih obveznosti za leti 2009 in 2010 se sprejmejo do 31. decembra 2010. Posamezne pravne zaveze v skladu s poglavjem IIa se sprejmejo do 31. marca 2011.

▼M1

3.  Finančni posredniki, opisani v Prilogi II, si prizadevajo za razdelitev vseh razpoložljivih sredstev, ki jih Unija namenja instrumentu za programe naložb in tehnični pomoči projektom za energetsko učinkovitost in obnovljivo energijo, do 31. marca 2014. Po tem datumu se sredstva, ki jih Unija namenja instrumentu, ne dodeljujejo več. Vsa sredstva Unije, ki jih finančni posredniki do 31. marca 2014 niso dodelili, se vrnejo v splošni proračun Unije. Sredstva Unije, ki so bila dodeljena programom naložb, so lahko naložena za določeno obdobje, ki traja najpozneje do 31. marca 2034. Unija ima pravico do donosa za svoje naložbe v instrument za obdobje trajanja instrumenta sorazmerno s svojim vložkom v instrument in skladno s svojimi delničarskimi pravicami.

▼B

1. Pregled

,
Naslov Regulativa
Article 3 1.

The financial envelope for the implementation of the EEPR for 2009 and 2010 shall be EUR 3 980 000 000 , allocated as follows:

(a) 

gas and electricity infrastructure projects: EUR 2 365 000 000 ;

(b) 

offshore wind energy projects: EUR 565 000 000 ;

(c) 

carbon capture and storage projects: EUR 1 050 000 000 .

Article 3 2.
Individual legal commitments under Chapter II implementing the budgetary commitments made in 2009 and 2010 shall be made by 31 December 2010. Individual legal commitments under Chapter IIa shall be made by 31 March 2011.
Article 3 3.
The financial intermediaries described in Annex II shall endeavour to allocate all the funding from the Union contribution available in the facility to investment projects and to technical assistance for energy efficiency and renewable energy projects by 31 March 2014. No funding from the Union contribution shall be allocated after that date. All funding from the Union contribution not allocated by the financial intermediaries by 31 March 2014 shall be returned to the general budget of the Union. The funding from the Union contribution allocated to investment projects shall remain invested for a specified length of time that may not extend beyond 31 March 2034. The Union shall be entitled to returns on its investment in the facility throughout the lifetime of the facility, in proportion to its contribution to the facility and in accordance with its shareholder rights.

1.1 Sklici

1.2 Ugotovljene zahteve

1.3 Povezani standardi

2. Ugotovljene zahteve

Zahteve
Vir Zahteva

3. Povezani standardi

Standardi
Vir Zahteva
  • Builddate: 24.12.2018 00:00:00 -Doknr: CELEX:32009R0663
  • EULAW -

    EN: Legal acts of the European Union from EUR-Lex, https://eur-lex.europa.eu/. © European Union. Re-use is authorised by Decision 2011/833/EU, provided the source is acknowledged; the consolidated texts are licensed under CC BY 4.0 (EUR-Lex legal notice). Divided into sections and converted into the GRCA format, the wording unchanged. Only the legislation published in the Official Journal of the European Union is deemed authentic.

    DE: Rechtsakte der Europäischen Union aus EUR-Lex, https://eur-lex.europa.eu/. © Europäische Union. Weiterverwendung nach Beschluss 2011/833/EU mit Quellenangabe gestattet; die konsolidierten Fassungen stehen unter CC BY 4.0 (Rechtlicher Hinweis von EUR-Lex). In Abschnitte aufgeteilt und in das GRCA-Format umgewandelt, der Wortlaut unverändert. Verbindlich sind allein die im Amtsblatt der Europäischen Union veröffentlichten Rechtsakte.