+Člen 19 Merila za izbiro in dodelitev
---+Article 19 1.
---+Article 19 2.

Člen 19 Merila za izbiro in dodelitev

Člen 19

Merila za izbiro in dodelitev

1.  Pri oceni predlogov, prejetih na podlagi razpisa za zbiranje predlogov iz člena 17(2), Komisija uporabi naslednja merila izbire:

(a) utemeljenost in tehnična primernost pristopa;

(b) zrelost, kar pomeni, da je projekt v naložbeni fazi, kar zajema tudi raziskovanje in razvoj možnosti za shranjevanje, v zvezi z njim pa bodo do konca leta 2010 nastali znatni izdatki, povezani z naložbami;

(c) trdnost finančnega paketa za celotno naložbeno fazo projekta;

(d) identifikacija vseh potrebnih dovoljenj, potrebnih za gradnjo in delovanje projekta na predlaganem mestu (-ih) in obstoj strategije za zaščito teh dovoljenj.

2.  Pri oceni predlogov, prejetih na podlagi razpisa za zbiranje predlogov iz člena 17(2), Komisija uporabi naslednja merila za dodelitev:

(a) v kolikšnem obsegu nezadosten dostop do virov financiranja zavira izvajanje ukrepov;

(b) zahtevano financiranje na tono CO2, ki se zmanjša v prvih petih letih delovanja projekta;

(c) zapletenost projekta in raven inovacij celotnega obrata, vključno z drugimi spremljajočimi raziskovalnimi dejavnostmi, kot tudi zavezanost, ki jo izkažejo upravičenci za širjenje rezultatov tehnološkega napredka projekta drugim evropskim izvajalcem na način, ki je skladen z zakonodajo Skupnosti in zlasti s cilji in strukturami, začrtanimi v Evropskem strateškem načrtu za energetsko tehnologijo;

(d) utemeljenost in primernost načrta upravljanja v zvezi z znanstvenimi in tehničnimi informacijami in podatki, ki jih vsebuje, kot dokaz za ustrezno pripravljenost zasnove, da projekt začne delovati do 31. decembra 2015.

1. Pregled

,
Naslov Regulativa
Article 19 1.

In assessing the proposals received under the call for proposals referred to in Article 17(2), the Commission shall apply the following selection criteria:

(a) 

the soundness and technical adequacy of the approach;

(b) 

maturity, defined as reaching the investment stage, which includes exploration and development of storage options, and incurring substantial investment-related expenditure for the project by the end of 2010;

(c) 

the soundness of the financial package for the full investment phase of the project;

(d) 

identification of all necessary permits required for construction and operation of the project at the proposed site(s) and the existence of a strategy to secure those permits.

Article 19 2.

In assessing the proposals received under the call for proposals referred to in Article 17(2), the Commission shall apply the following award criteria:

(a) 

the extent to which lack of access to finance is delaying the implementation of the action;

(b) 

requested funding per tonne of CO2 to be abated in the first five years of operation of the project;

(c) 

the complexity of the project and level of innovation of the overall installation including other accompanying research activities and the commitment demonstrated by the beneficiaries to disseminate to other European operators the results of the technological advances made by the project in a manner compatible with Community law and in particular with the objectives and structures outlined in the Strategic Energy Technology Plan for Europe;

(d) 

the soundness and adequacy of the management plan including, in relation to the scientific, engineering and technical information and data contained therein, demonstration of readiness of the proposed concept to achieve operation of the project by 31 December 2015.

1.1 Sklici

1.2 Ugotovljene zahteve

1.3 Povezani standardi

2. Ugotovljene zahteve

Zahteve
Vir Zahteva

3. Povezani standardi

Standardi
Vir Zahteva
  • Builddate: 24.12.2018 00:00:00 -Doknr: CELEX:32009R0663
  • EULAW -

    EN: Legal acts of the European Union from EUR-Lex, https://eur-lex.europa.eu/. © European Union. Re-use is authorised by Decision 2011/833/EU, provided the source is acknowledged; the consolidated texts are licensed under CC BY 4.0 (EUR-Lex legal notice). Divided into sections and converted into the GRCA format, the wording unchanged. Only the legislation published in the Official Journal of the European Union is deemed authentic.

    DE: Rechtsakte der Europäischen Union aus EUR-Lex, https://eur-lex.europa.eu/. © Europäische Union. Weiterverwendung nach Beschluss 2011/833/EU mit Quellenangabe gestattet; die konsolidierten Fassungen stehen unter CC BY 4.0 (Rechtlicher Hinweis von EUR-Lex). In Abschnitte aufgeteilt und in das GRCA-Format umgewandelt, der Wortlaut unverändert. Verbindlich sind allein die im Amtsblatt der Europäischen Union veröffentlichten Rechtsakte.