+Article 16a 5.

Article 16a 5.

Following the screening process, the applications referred to in paragraph 3 of this Article shall be authorised from an environmental perspective without requiring any express decision from the competent authority, unless the competent authority adopts an administrative decision, setting out due reasons on the basis of clear evidence, to the effect that a specific project is highly likely to give rise to significant unforeseen adverse effects in view of the environmental sensitivity of the geographical area where the project is located that cannot be mitigated by the measures identified in the plans designating acceleration areas or proposed by the project developer. Such decisions shall be made publicly available. Such renewable energy projects shall be subject to an environmental impact assessment pursuant to Directive 2011/92/EU and, if applicable, to an assessment pursuant to Directive 92/43/EEC, which shall be carried out within six months of the administrative decision identifying a high likelihood of significant unforeseen adverse effects. Where duly justified on the grounds of extraordinary circumstances, that six-month period may be extended by up to six months.

In the event of justified circumstances, including where needed to accelerate the deployment of renewable energy to achieve the climate and renewable energy targets, Member States may exempt wind and solar photovoltaic projects from such assessments.

Where Member States exempt wind and solar photovoltaics projects from those assessments, the operator shall adopt proportionate mitigation measures or, where such mitigation measures are not available, compensatory measures, which, if other proportionate compensatory measures are not available, may take the form of monetary compensation, in order to address any adverse effects. Where those adverse effects have an impact on species protection, the operator shall pay a monetary compensation for species protection programmes for the duration of the operation of the renewable energy plant in order to ensure or improve the conservation status of the species affected.

1. Prezentare generală

,
Titlu Reglementare

1.1 Referințe

1.2 Cerințe identificate

1.3 Standarde asociate

2. Cerințe identificate

Cerințe
Sursă Cerință

3. Standarde asociate

Standarde
Sursă Cerință
  • Builddate: 16.07.2024 00:00:00 -Doknr: CELEX:32018L2001
  • EULAW -

    EN: Legal acts of the European Union from EUR-Lex, https://eur-lex.europa.eu/. © European Union. Re-use is authorised by Decision 2011/833/EU, provided the source is acknowledged; the consolidated texts are licensed under CC BY 4.0 (EUR-Lex legal notice). Divided into sections and converted into the GRCA format, the wording unchanged. Only the legislation published in the Official Journal of the European Union is deemed authentic.

    DE: Rechtsakte der Europäischen Union aus EUR-Lex, https://eur-lex.europa.eu/. © Europäische Union. Weiterverwendung nach Beschluss 2011/833/EU mit Quellenangabe gestattet; die konsolidierten Fassungen stehen unter CC BY 4.0 (Rechtlicher Hinweis von EUR-Lex). In Abschnitte aufgeteilt und in das GRCA-Format umgewandelt, der Wortlaut unverändert. Verbindlich sind allein die im Amtsblatt der Europäischen Union veröffentlichten Rechtsakte.