+Article 5 2

Article 5 2

2.   Member States shall take the necessary measures to ensure that, as of 1 January 2024, no existing medium combustion plant with a rated thermal input greater than 5 MW is operated without a permit or without being registered.

Member States shall take the necessary measures to ensure that, as of 1 January 2029, no existing medium combustion plant with a rated thermal input of less than or equal to 5 MW is operated without a permit or without being registered.

1. Prehľad

,
Názov Regulácia

1.1 Odkazy

1.2 Identifikované požiadavky

1.3 Súvisiace štandardy

2. Identifikované požiadavky

Požiadavky
Zdroj Požiadavka

3. Súvisiace štandardy

Štandardy
Zdroj Požiadavka